NRC Finishes TerraPower’s Construction Permit Ahead of Schedule

In a welcoming milestone, TerraPower received approval from the Nuclear Regulatory Commission (NRC) for a construction permit for its advanced nuclear power plant in Kemmerer, Wyoming. The review, completed ahead of schedule, provides a hopeful signal that the United States is finally turning the corner on one of the biggest barriers to clean energy innovation: an outdated, slow, and unpredictable licensing and permitting system. 

In a welcoming milestone, TerraPower received approval from the Nuclear Regulatory Commission (NRC) for a construction permit for its advanced nuclear power plant in Kemmerer, Wyoming. The review, completed ahead of schedule, provides a hopeful signal that the United States is finally turning the corner on one of the biggest barriers to clean energy innovation: an outdated, slow, and unpredictable licensing and permitting system. 

NRC’s decision allows TerraPower to begin nuclear construction on what will be the first commercial advanced reactor permitted in decades. The Natrium design is a sodium-cooled reactor paired with molten-salt energy storage, capable of producing 345 megawatts of electricity and ramping up to roughly 500 megawatts during demand spikes. The molten salt battery gives the plant the flexibility to ramp up as needed. As electricity demand increases from data center growth, industrial consumption, and increased electrification, advanced nuclear can help provide affordable, dispatchable power. 

For decades, America has talked about the promise of advanced nuclear energy. Smaller designs, improved safety characteristics, flexible output, and the potential for factory-based manufacturing could make nuclear power more affordable and deployable.  While cost competitiveness has always been a concern, the reality is that government policy and antiquated regulations have inflated nuclear energy’s costs. 

Recent bipartisan efforts in Congress (NEIMA in 2019 and the ADVANCE Act in 2024) include provisions to modernize licensing and permitting, increase international collaboration, and reduce costs for investment and deployment. The bipartisan ADVANCE Act directed the NRC to reduce licensing fees, strengthen its capacity to review advanced technologies, and streamline approvals for reactors built at existing power plant sites or other brownfield locations. Furthermore, the Trump administration has taken steps to right-size regulations that impose unnecessary costs and slow the pace of innovation and investment. 

>>>READ:: Reforming Radiation Standards to Unlock Nuclear Energy’s Full Potential

To be clear, the process remains rigorous and time-consuming. TerraPower engaged in years-long pre-application work with the NRC, dating back to 2022.  The company submitted its construction permit in March 2024, which the NRC accepted two months later. The NRC targeted August 2026 to complete the review, but finished several months ahead of schedule. Even with its construction permit in place, TerraPower must obtain a separate operating license before the plant can generate electricity, a process expected later this decade. The plant likely won’t be online until at least 2031.

Nevertheless, the approval to start building marks two important milestones. It is the first construction approval of a commercial nuclear reactor in nearly a decade and the first one for a non-light-water reactor in nearly four decades. Critically, the NRC followed a performance-based, risk-informed review. With a variety of small modular and advanced reactors, it will be essential for the licensing and permitting process to be technology-neutral, risk-informed, and flexible. Reviews of applicants should be specific to the technology, not broad, blanket requirements that have little to do with assessing risk and performance for that technology. 

If regulators get that right, the Natrium reactor in Wyoming will not be remembered as an isolated success. It will be remembered as the moment when advanced nuclear finally began moving from promise to deployment in the United States.

Avatar photo

About the author

Nick Loris

Nick Loris is President of C3 Solutions, where he writes about energy and climate policy, from natural resource development and nuclear power to energy subsidies and environmental innovation. His work explores how markets can help reduce emissions, improve environmental outcomes and strengthen communities’ ability to adapt to a changing climate. Before joining C3 Solutions, Loris held senior energy policy roles at The Heritage Foundation. He has testified before House and Senate committees, and his work has appeared in *The Wall Street Journal* and *The New York Times*. He holds a master’s degree in economics from George Mason University. Loris is also an Energy Fellow at the Abundance Institute, a Senior Policy Fellow at the National Taxpayers Union, and a board member of the American Power Play Institute and the Energy Infrastructure Alliance Forum.

More from this writer →

Introducing C3 Journal

A new Journal. A bigger conversation.

C3 News Mag is now C3 Journal—a complete rethink of what an energy and environmental publication can be. Original essays. Leading contributors. The issues that matter, examined by some of America’s best policy minds. Built for the people making consequential decisions about energy, the environment, and our shared future.

C3 News Mag is now C3 Journal. A new home for original essays, leading policy minds, and the ideas shaping energy and the environment.

Get Field Notes, the C3 Journal newsletter.